September 25 Update

by necmusic

As NEC works to complete installation of HVAC and emergency generator equipment, the Conservatory community should be aware that we will be setting up a crane on Huntington Ave. to hoist equipment and steel dunnage (support materials) to the Jordan Hall roof on a nighttime and weekend schedule. Beginning Thursday, September 27, three hoisting operations will take place as follows:

Thursday 9-27-12 hoisting and rigging 7:00 pm to 6:00 am
Saturday 9-29-12 hoisting and rigging 7:00 am to 3:00 pm
Third lift to be determined

During nighttime operations extra safety and lighting measures will be implemented per City of Boston and OSHA requirements. During the day on Saturday, September 29, 10 parking meters on Huntington Ave. will be taken out of service. Police details will also be on Huntington to assist with traffic flow.

All safety steps for our students, faculty and staff will be put in place and monitored throughout these operations by Mike Ryan, Director of Operations, the Building Operations staff , and Tishman Construction.

About these ads